Major Projects under Implementation.

Ongoing projects:

Sl. NoDivisionParticularsDescription
1EAP“Construction of Imphal Kangchup Tamenglong Road” with assistance from Asian Development Bank (ADB)The road is constructed under SASEC Road Connectivity Investment Program and forms a part of the Imphal Tamenglong Haflong Road...... Read More
2NEC-IIRehabilitation & Upgradation of Road from Kamjong to Konkan Thana via PilongThe existing road is being upgraded as an Intermediate Double Lane (5.5m) road under the funding from MDoNER, Govt of India. The road provides access to the trading kiosk with Myanmar at Konkan Thana at the border.
3NH-IIIConstruction of 4-lane Elevated Corridor Project for a length of 25.00 km on NH-02 & 102 (Starting from Koirengei to Airport & Manipur University)Included in the Ministry's approved list of work to be taken up during FY 2022-23 for an amount of Rs. 3000.00 Crore
4NH – ILA/Preconstruction Activities from Km 0.00 to Km 44.509 under Annual Plan 2022-23(a) Consultancy services for feasibility study and DPR preparation is in progress
(b) LA process (1) 3a Gazette notification publised on 22.03.2022 (2) Types & Nature of land of Imphal West and Kakching District submitted to concerned CALAs for approval aploading in Bhumirashi portal for 3A notification.
5NH - IILA/Preconstruction Activities from Km 0.00 to Km 202.00 under annual Plan 2022-23under Annual Plan 2022-23

Pipeline Projects:

Sl. No.ParticularsDescription
1“Construction of Imphal Ring Road”The Ring Road which will be funded by ADB, besides addressing the traffic congestion shall provide rapid transport corridor with access to all the major administrative institution and commercial centres. This will also facilitate expansion of the city, decentralising and decongesting the present core zone of the city in line with the Un ion Govt’s policy of urban development.
2“Improvement of Roads within Imphal City with Rigid Pavement including Concrete Lined Drains” – Imphal East & Imphal WestThe proposed road project shall be the solution for sustainable road infrastructure in the Greater Imphal zone of the state capital.
3Manipur State Roads Improvement ProgramState has sought assistance from ADB through Dept. of Economic Affairs, Ministry of Finance, Govt. of India for Consultancy Service for a Road Master Plan with a horizon of 10 years.
4Elevated Corridor for 25Km on NH-02 & 102Elevated Highway will provide swift mobility to the specific destination-bound traffic like airport, new civil secretariat, High Court etc, without having to negotiate with highly congested traffic in the city centre.

Projects in Concept Stage.

Sl. NoParticular Description
1Major Projects proposed for inclusion as part of the National Connectivity Infrastructural Development Project by the Ministry of Road Transport and Highways under Bharat Mala – II
i.Trans Manipur Highways
ii.Liklang Pareng
The major objective of the proposed project is to provide accessibility to the international Border with Myanmar
The proposed road project shall provide direct and shortest connectivity among hill districts Head Quarters and enhance accessibility to poorly connected remote villages in the Hill districts.

Major Projects above 100 Crore.

Details of project with estimated cost of Rs.100 crore or more.

Sl.No.Name of ProjectsSanctioned amount (Rs. in crore)Description
EAP
1“Construction of Imphal Kangchup Tamenglong Road” with assistance from Asian Development Bank (ADB)1437.44
Jiribam Division (under ISC Scheme)
2Construction of road from Km 0.00 to Km 32.31 (Ph-I: 32.31 Km) on Jiribam (on NH-37 at Manipur/Assam Border) to Manipur / Mizoram Border Section via Tipaimukh under ISC Scheme in Manipur.114.14Tender under process
NEC Division
3Rehabilitation and upgradation of road from Kamjong to Konkan Thana via Pilong (Length-37.33 km)112.74UC for Rs.8526.41 already submitted
4Improvement /upgradation of Henglep Thingkhew Tipaimukh road (Length-31.782 km)115.39Tender evaluation in Progress

PIU/EAP

I.Completed Projects (475.68)

1.MN06CW1: Tupul to Bishnupur – 50.80 Km)

(a) Externally Aided Project (EAP) under MDoNER, Govt. of India (GoI). The work has been completed. Rs. 15.69 Crore released by MDoNER for refund of Retention Money of Contractor is pending with the State Govt.

2.MN06CW2: Thoubal to Kasom Khullen – 47.125 km

(b) Rs. 1.00 Crore required as State Share during 2022-23 for meeting expenditure of Construction Supervision Consultant during the Defect Liability Period.

II.Ongoing Projects

Construction of Imphal Kangchup Tamenglong Road

1. Section A (Km 0.00 to Km 34.60) & Section B (Km 72.30 to Km 103.02) – 65.32 km (1437.44)

(a) EAP funded by Asian Development Bank through GoI with funding share of 90.10. Rs. 30.00 Crore released by GoI is pending with State Govt.

2.Lot 1 (Km 34.60 to Km 51.00) – 20.55 km (1437.44)

(b) State Govt. has providied a Gap Funding of Rs. 70.00 Crore for the project

3.Lot 2 (Km 51.00 to Km 72.30) – 22.10 Km (1437.44)

III.Pipeline Projects

1.Construction of Imphal Ring Road – 51.23 km (1398.16)

The project has been posed to ADB for US$122 Million. ADB had fielded two Missions and another Mission is scheduled for 19.05.2022 to 23.05.2022. All preparatory works are completed and tenders under advance contracting are to be floated within 2nd/3rd Quarter of current year.

2.Improvement of roads within Imphal City with Rigid Pavement including Concrete Lined Drains – 550 km (N/A)

The project has been posed to DEA, GoI for reconsideration for an Investment Loan of Rs. 3303.75 Crore from Asian Infrastructure Investment Bank. All Line Ministries have conveyed “No Objection” to the proposal. The State Govt. has taken up the Consultancy Services for Feasibility Study and DPR Preparation of the project for the cost of Rs. 14.04 Crore from its own sources.

3.Manipur State Roads Improvement Program – 400 km(N/A)

The project is being implemented into two phases i.e. Consultancy Services for Feasibility Study & Preparation of DPR and Implementation of the project. Terms of Reference for Consultancy Services for preparation of Feasibility Study & DPR for the project have been submitted to ADB for approval. The project will be then proposed as an Investment Loan to ADB or other funding agencies for improvement of 400 km important roads in the State with an estimated cost of Rs. 3044 Crore.

 

Information on the Contractors that Participated in Bidding for the Contract Packages Valuing more than 70.00 Crore during 01-04-2017 to 31-03 202) under PWD Manipur

Sl.No.DivisionPackage NumberPackage NameCost Estimate (in INR Crore)
A. STATE PWD
1Externally Aided Projects, PWD ManipurIKTR Section IIA (LOT 1)Construction of Imphal Kangchup Tamenglong Road Section IIA (Km. 34+600 to Km. 51+000) (Lot 1)206.32
2Externally Aided Projects, PWD ManipurIKTR Section IIB (LOT 2)Construction of Imphal Kangchup Tamenglong Road Section IIB (Km. 51+000 to Km. 72+300) (Lot 2)206.35
3National Highway Division - IIJob No: 102A/MN/2019-20/30Restoration and Rehabilitation of road from km 134/00 to km 202/00 (length = 68 km) on NH-102 A i/c protection/slide slope works by retaining walls etc. essential places and 50 nos of HP culverts in the state of Manipur on EPC mode71.11
4National Highway Division - IIJob No: 102A/MN/2020-21/33Restoration and Rehabilitation of road from km 00/00 to km 83/50 (length = 83.50 km) on NH-102 A i/c protection/slide slope works by retaining walls etc. essential places and 83 nos of HP culverts in the state of Manipur on EPC mode72.58
5National Highway Division - IIJob No:102A/MN/2020-21/34Strengthening and widening from km 320.320 to km 330.00 on NH-102, Imphal Moreh Section during the year 2020-21 in the State of Manipur70.86
6National Highway Division - IIIJob No. 150/MN/2016-17/016Widening of existing 2/4 lane to 6-lane multi lane from km 454.798 to km 459.600, widening of formation from km 474.00 to km 488.00 and providing paved shoulder including strengthening of the existing pavement from km 465.20 to km 488.00 during 2016-17 in the state of Manipur99.49
7National Highway Division - IIIJob No. 150/MN/2016-17/017Strengthening of existing two lane pavement i/c paved shoulder on NH-150 from km 433.00 to km 454.798 in the state of Manipur during 2016-1798.8
8National Highway Division - III Job No. 150/MN/2016-17/014Strengthening of existing two lane pavement i/c paved shoulder on NH-150 from km 412.00 to km 433.00 in the state of Manipur during 2016-17 89.56
9National Highway Division - IJob No. 039/MN/2016-17/20 dt. 3-01-2017Strengthening of existing pavement including paved shoulder from km 304.00 to km 318.840 of NH-39,Mao -Imphal section in the State of Manipur.70.5697803
10National Highway Division - IJob No. 039/MN/2016-17/19 dt. 30-11-2016Strengthening of existing two lane pavement i/c Construction of paved shoulder on NH-39(SH:- Mao-Imphal section from km 212.325 to km 260.000) on EPC mode in the state of Manipur during 2016-17.177.22
11National Highway Division - IJob No. 039/MN/2016-17/18 dt. 30-11-2016Strengthening of existing two lane pavement i/c Construction of paved shoulder from km 260.00 to km 299.00 on NH-39(New Nnh-02)Mao-Imphal section (SH:- km 260.00 to km 287.00) in the state of Manipur on EPC mode.107.56
12North Eastern Council - IIN/ARehabilitation and upgradation of road from Kamjong to Konkan Thana Road via Pilong (L = 37.33 km)137.78
13North Eastern Council - IIN/AImprovement/Upgradation of Henglep Thingkhew Tipaimukh Road (Length = 31.782 km)110.97